Cure

verbStandard termRefractories

To hold freshly placed castable moist and at moderate temperature so its cement can fully hydrate.

To let a placed castable set and gain strength before any heat-up, typically for at least 24 hours at roughly 15 to 30 C, kept from drying out. Below about 10 C the cement sets and gains strength slowly, and hot, windy conditions dry the surface too fast. Cure time and temperature are logged, because a poorly cured lining is prone to cracking and spalling during dry-out.

Heard on the job

Tarp it and keep the heaters on, it has to cure 24 hours above 15 C before we fire.

Insider tip

Cold-weather pours need heated enclosures. Castable that freezes before it cures is scrap, even if it looks fine.

Also heard as

  • curing