Break

nounShop talkConcrete

A cylinder strength test result, or the crushing of cylinders in the lab.

Engineers, supers and testing techs talk in breaks: 7-day breaks, 28-day breaks, the hold, a low break. Seven-day results usually land around 65 to 75 percent of the 28-day strength for a straight cement mix and lower for heavy SCM blends, so a weak 7-day number is an early warning. A low 28-day break sets off cores, extra holds and arguments about who added water.

Heard on the job

Seven-day breaks came in at 2,600 on a 4,000 mix, call the plant and ask what changed.

Insider tip

The hold is a spare cylinder kept unbroken until the 28-day results are in, then broken to check a suspect low result or at 56 days for information.

Also heard as

  • breaks
  • cylinder break
  • 7-day
  • 28-day