Breakdown roller

nounStandard termAsphalt

The first roller behind the paver, which does most of the compaction while the mat is still hot.

The lead compactor, usually a double-drum vibratory steel roller, working close behind the screed while the mat is at its hottest. It achieves most of the density gain, taking the mat from the screed's 80 percent or so to within a couple of points of target. Breakdown rolling has to happen before the mix stiffens, so the operator watches mat temperature and the paver's pace rather than the clock.

Heard on the job

Breakdown roller's falling behind, get him up on the screed, he's rolling 220-degree mat back there.

Also heard as

  • breakdown
  • lead roller