Takt time

nounStandard termProduction

The maximum allowable time to produce one unit in order to meet customer demand.

Takt time is the heartbeat of a lean manufacturing system. It is calculated by dividing the total available production time by the number of units the customer requires in that period. If the takt time is two minutes, a finished product must roll off the line every two minutes. Operating faster than takt time creates excess inventory, while operating slower results in missed orders.

Heard on the job

The client increased their order volume, so we need to recalculate our takt time and probably add a shift.

Insider tip

Never confuse takt time with cycle time. Takt time is what the customer demands; cycle time is what your equipment actually does.

Do not mix it up with

  • Makespan: Takt time is the required pace based on demand, while makespan is the total actual time it takes to complete a specific batch or job.