PT

abbreviationStandard termConcrete

Post-tensioning: reinforcing concrete with steel tendons that are stretched tight after the concrete hardens.

Post-tensioning places high-strength strand in sheathing or ducts before the pour and jacks it to high tension once the concrete is strong enough, squeezing the member into compression so it spans farther with less depth and cracking. US building slabs and parking decks mostly use unbonded monostrand tendons, while bridges and heavy structures use bonded, grouted multistrand systems. Cutting or coring a PT slab without locating the tendons first can release a strand with lethal force.

Heard on the job

It's a PT deck, so nobody drills, cores or shoots a pin into it until the GPR guy marks the tendons.

Also heard as

  • post-tensioning
  • post-tensioned concrete