N-1 criterion

nounStandard termElectrotechnology

Planning rule that a grid must stay within limits after losing any single major element such as a line or generator.

The N-1 criterion requires that, starting from a normal state with all N elements in service, the system can lose any one line, transformer, generator or busbar section without overloads, voltage violations, instability or loss of load beyond what is allowed. Planners and real-time operators run contingency analysis continuously against it. Tighter rules cover a second loss: N-1-1 for one that arrives after the first has been dealt with, N-2 for two at once.

Heard on the job

If we take the Westside line out for maintenance we're no longer N-1 secure on the north import, so it waits until the new cable is in.

Insider tip

When a dispatcher says the system is 'not N-1', one more trip will cause real trouble, and routine switching gets postponed.

Also heard as

  • N minus one
  • single contingency criterion